Award of Decarbonisation Contracts (Forward Plan Reference FP1046)

Decision Maker: Cabinet

Decision status: Recommendations approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Agreement to dispense with Contract Procedure Rules to make a direct award.

Decision:

(1)   That in accordance with paragraph 14k (Alternative Procedures in Prescribed Circumstances) of the Contract Procedure Rules, that Cabinet agree to appoint Design Installation Service Limited to act as Principal Contractor with a separate appointment to Barry Beard Limited to undertake work in 2021 in accordance with the information and reasons contained in the report.

 

(2)   Cabinet approved the drawdown of £196k from earmarked reserves for the council’s contribution towards the total project cost of £2.559M. The remaining £2.363M of costs will be met by grant funding received. 

Publication date: 18/06/2021

Date of decision: 15/06/2021

Decided at meeting: 15/06/2021 - Cabinet

Effective from: 25/06/2021