STREETSCENE MOBILISATION UPDATE

Meeting: 09/07/2019 - Cabinet (Item 23)

23 STREETSCENE MOBILISATION UPDATE pdf icon PDF 190 KB

Report of the Corporate Director (Resources, Environment and Cultural Services) providing an update on the work of the Board.

Decision:

(1)     The Cabinet agreed that the start of both contracts (namely Waste Collection and Cleansing and Grounds Maintenance) would be on or around Saturday 28 March 2020.

 

(2)     Delegated authority was given to the Corporate Director (Resources, Environment and Cultural Services), in consultation with Executive Member (Environment and Planning), to finalise the Service Level Agreement with Hertfordshire County Council.

Minutes:

Report of the Corporate Director (Resources, Environment and Cultural Services) providing an update on the work of the Board.

 

In June 2019, the Cabinet agreed that a Member led mobilisation Board should be established to oversee the commencement of the new Streetscene contracts and the Tewin Road depot procurement.

 

RESOLVED:

 

(1)     That the Cabinet agrees that the start of both contracts (namely Waste Collection and Cleansing and Grounds Maintenance) would be on or around Saturday 28 March 2020.

 

(2)     That delegated authority be given to the Corporate Director (Resources, Environment and Cultural Services), in consultation with Executive Member (Environment and Planning), to finalise the Service Level Agreement with Hertfordshire County Council in line with the summary in Appendix 1 of the report.