49 Internal Refurbishment Works - Chilton Green (Forward Plan Reference FP1135) pdf icon PDF 129 KB

Report of the Service Director (Property Maintenance and Climate Change) considering the procurement process undertaken for the refurbishment of the Chilton Green scheme.

Additional documents:

Decision:

Cabinet agreed that the contract for the refurbishment of Chilton Green is awarded to Mulalley and Co Limited.

Minutes:

Report of the Service Director (Property Maintenance and Climate Change) considering the procurement process undertaken for the refurbishment of the Chilton Green scheme.

 

(1)         The Decision Taken

 

RESOLVED:

(unanimous)

 

Cabinet agreed that the contract for the refurbishment of Chilton Green is awarded to Mulalley and Co Limited.

 

(2)         Reasons for the Decision

 

The report set out a recommendation to appoint Mullalley and Co Ltd to carry out the refurbishment of the Chilton Green Sheltered Scheme.

 

The works included replacing the fire alarm and upgrading works to communal areas including a new kitchen, new laundry and communal doors together with replacement floor coverings and decorating.

 

The project had been procured in accordance with the Council’s Contract Procedure Rules and Public Contracts Regulations 2015. Nine bids were received and Mullaley and Co were the highest scoring bidder.

 

(Note: Cabinet agreed both the Part 1 and Part 2 decision for this item so a confidential discussion in Part 2 was not needed).