FP2078 Housing Planned Works (Internals) Contract
Report of the Executive Director (Resident Services and Climate Change)
Additional documents:
Decision:
Decision taken
Cabinet agreed to award the contract for Internal planned work to Gracelands Complete Maintenance Services to commence on 1st February 2025 and continue for an initial period of 3 years with a possible extension of up to 5 years.
Reason for decision
Details for the reason for decision are set out at paragraph 329.1
Minutes:
Cabinet received a report on the award of a contract for the planned internal works.
Decision taken
Cabinet agreed to award the contract for Internal planned work to Gracelands Complete Maintenance Services to commence on 1st February 2025 and continue for an initial period of 3 years with a possible extension of up to 5 years.
Reason for decision
Details for the reason for decision are set out at paragraph 329.1