Decision Maker: Cabinet
Decision status: Recommendations approved
Is Key decision?: Yes
Is subject to call in?: Yes
To award contract.
Exempt report of the Corporate Director (Housing and Communities) on the cladding works at Queensway House.
(1) The Decision Taken
RESOLVED:
(unanimous)
(1) That pursuant to Contract Procedure Rule 14 (k) (Alternative Procedures in Prescribed Circumstances) Cabinet agreed to waive the requirement for a competition to be carried out and for five (5) tenders to be obtained, on the basis that it is to the advantage of the Council that the rule should be waived”;
(2) Cabinet approved the direct award of contract to Borras Construction Limited for Phase 2 Cladding Removal at Queensway House.
(2) Reasons for the Decision
The report asked Members to approve the recommendations in item 2 to directly award the contract to Borras Construction Limited in accordance with section 14k (Alternative Procedures in Prescribed Situations) of the Contract Procedure Rules.
The cost to undertake the Phase 2 cladding removal is based on the phase 1 cost and specification.
Report author: Peter Gray
Publication date: 11/09/2020
Date of decision: 08/09/2020
Decided at meeting: 08/09/2020 - Cabinet
Effective from: 18/09/2020